Battery storage at existing solar site, Windham Road 13

Council supported the project for procurement on Nov. 25, 2025.

Council approved a municipal support resolution.

Municipality
Norfolk County
Decided by
Council
Meeting date
Developer
Skyline Clean Energy
Type
Battery storage
Size
30 MW
Procurement
IESO LT2 Window 1 (Capacity)
Vote
Not reported in the source

What this decision does and does not do

A support resolution or confirmation lets the developer bid into an IESO procurement. It is not a planning approval: zoning, site plan and provincial permits still apply if the project wins a contract.