Civic Evidence

Decisions / City of North Bay

Bruman North Bay Generation

Council supported the project for procurement on Nov. 25, 2025.

Council approved a municipal support resolution for Northern Ontario Capacity's proposed 9.9 MW natural-gas generation facility at 1141 Carmichael Drive. City By-law 2025-101, enacted November 25, 2025, authorizes the mayor and clerk to sign the resolution. This establishes municipal support for an IESO LT2 bid, not an IESO contract award, zoning approval or construction permit. The cited by-law does not report the vote count.

Municipality
City of North Bay
Decided by
Council
Meeting date
Developer
Northern Ontario Capacity (NOC) – Bruman North Bay
Type
Natural gas
Size
9.9 MW, Proposed distribution-connected natural-gas generation capacity; not an IESO contract award.
Procurement
IESO LT2 (window not specified in the cited city by-law or report)
Vote
Not reported in the source

What this decision does and does not do

A support resolution or confirmation lets the developer bid into an IESO procurement. It is not a planning approval: zoning, site plan and provincial permits still apply if the project wins a contract.

Sources

Official municipal recap linked; detailed minutes may be absent. About evidence classifications.

Spot an error? Send a correction with a link to the record that shows it.