West Carleton March BESS (1500 Thomas Argue Road)
Council supported the project for procurement on Dec. 10, 2025.
Council granted a municipal support confirmation ahead of the December 18, 2025 capacity-stream deadline.
- Municipality
- City of Ottawa
- Decided by
- Council
- Meeting date
- Developer
- West Capital Power
- Type
- Battery storage
- Size
- Not reported
- Procurement
- IESO LT2 Window 1 (Capacity)
- Vote
- Not reported in the source
What this decision does and does not do
A support resolution or confirmation lets the developer bid into an IESO procurement. It is not a planning approval: zoning, site plan and provincial permits still apply if the project wins a contract.
Sources
Official municipal recap linked; detailed minutes may be absent. About evidence classifications.
- IESO Long Term 2 (LT2) Procurement ProcessEngage Ottawa ยท Municipal decision summary
Spot an error? Send a correction with a link to the record that shows it.