Decisions / Prince Edward County
Prince Edward Solar 1 (Clarke Road, Picton)
Council supported the project for procurement on Sept. 2025.
Council passed a municipal support resolution so the project could bid before the October 16, 2025 deadline. Zoning and site plan approvals would still be needed if it wins a contract.
- Municipality
- Prince Edward County
- Decided by
- Council
- Meeting date
- (month only)
- Developer
- Prince Edward Solar 1 LP (Alectra Energy Solutions and Kruger Energy, with the Mohawks of the Bay of Quinte)
- Type
- Solar
- Size
- 15 MW
- Procurement
- IESO LT2 Window 1 (Energy)
- Vote
- Carried; vote count not reported
What this decision does and does not do
A support resolution or confirmation lets the developer bid into an IESO procurement. It is not a planning approval: zoning, site plan and provincial permits still apply if the project wins a contract.
Sources
No official decision minutes or municipal recap currently linked. A staff report alone does not establish a council vote. About evidence classifications.
- Two proposed solar farms receive support resolutions to move to IESOCounty Live, Sept. 10, 2025 ยท Third-party reporting or commentary
Spot an error? Send a correction with a link to the record that shows it.