Decisions / City of Richmond Hill
IESO LT2 municipal support confirmation process
Council set rules for future requests on April 8, 2026.
Council adopted staff report SRPBS.26.004's municipal process for administering IESO Long-Term RFP support confirmations. It delegated authority to the City Manager to support blanket municipal support resolutions in principle for solar projects on written recommendation of the Commissioner of Planning and Building Services, and directed staff to implement the application process. Council also enacted fee amendment By-law 39-26. This is a process and delegation decision, not municipal support for any named project, an IESO contract award, or a planning approval.
- Municipality
- City of Richmond Hill
- Decided by
- Council
- Meeting date
- Developer
- Not applicable
- Type
- Policy
- Size
- Not reported
- Procurement
- IESO Long-Term RFP municipal support confirmations (policy, not a project bid)
- Vote
- Carried; numerical vote count not recorded in council minutes
What this decision does and does not do
This sets how the municipality will handle future requests for support, including which technologies or locations it will consider.
Sources
Official meeting minutes linked. About evidence classifications.
- City Council Minutes C#06-26, April 8, 2026, item 15.1.5 (p. 8): adopted SRPBS.26.004 municipal processCity of Richmond Hill · Official meeting minutes
- By-law 39-26, enacted April 8, 2026, amending municipal planning fees for IESO requestsCity of Richmond Hill · Municipal decision summary
- SRPBS.26.004: Independent Electricity System Operator Long Term RFP municipal process (staff report)City of Richmond Hill · Official background (not proof of vote)
Spot an error? Send a correction with a link to the record that shows it.