Riverside Cogen combined heat and power project
Council supported the project for procurement on Oct. 20, 2025.
Windsor Council carried resolution CR411/2025 supporting Riverside Cogen LP's submission to the IESO LT2 capacity procurement, for the limited purpose of satisfying the procurement's municipal-support requirement. The proposed 23 MW natural-gas combined heat and power facility would supply electricity to the grid and steam to Hiram Walker at 2072 Riverside Drive East. The resolution was not an IESO contract award or municipal land-use approval.
- Municipality
- City of Windsor
- Decided by
- Council
- Meeting date
- Developer
- Riverside Cogen LP (CEM Engineering; Hiram Walker host)
- Type
- Natural gas
- Size
- 23 MW, 23 MW maximum proposed LT2 contract capacity in the proponent's October 2, 2025 public meeting records; not an IESO contract award.
- Procurement
- IESO LT2 Window 1 (Capacity, LT2(c-1))
- Vote
- Carried (CR411/2025; no recorded vote count)
What this decision does and does not do
A support resolution or confirmation lets the developer bid into an IESO procurement. It is not a planning approval: zoning, site plan and provincial permits still apply if the project wins a contract.
Sources
Official meeting minutes linked. About evidence classifications.
- City Council minutes, October 20, 2025, item 8.2 (CR411/2025), reproduced in November 10 agenda package, pp. 13–14City of Windsor · Official meeting minutes
- Riverside Cogen LT2 community engagement minutes, October 2, 2025 — 23 MW, natural gas CHP and siteRiverside Cogen LP / CEM Engineering · Third-party reporting or commentary
Spot an error? Send a correction with a link to the record that shows it.